Projects

Horizon Power 132kV Transmission Line

Client
Horizon Power
Sector
Power Networks & Transmission
Location
Karratha to Dampier

Upgrading critical transmission infrastructure to strengthen power security across the Pilbara Project snapshot

Services
  • Design
  • Construction
  • Testing & Commissioning
The Challenge

Future energy demand across the Pilbara continues to grow, requiring investment in critical infrastructure to strengthen network reliability and support long-term energy security.

To support this demand, the Western Australian Government invested more than $23 million, through Horizon Power, to upgrade the 132kV Transmission Line between Karratha and Dampier.

The transmission line forms a critical part of the Pilbara electricity network, connecting the Karratha Terminal Substation to the Dampier Substation and supporting the North West Interconnected System (NWIS).

The project focused on upgrading ageing infrastructure while improving long-term network reliability and visual amenity outcomes.

The Genus Approach

Genus was engaged to deliver the design, construction and commissioning of the transmission line upgrade.

The project involved replacement of ageing infrastructure, undergrounding sections of the line and reconfiguring the transmission corridor to improve network performance and reduce infrastructure footprint.

The upgrade also delivered improvements to town aesthetics through significant reductions in pole numbers.

Delivery in action

The project involved replacement and upgrade works across the existing transmission corridor.

The scope includes:

  • Removal and replacement of approximately 200 ageing timber poles with steel poles
  • Reconfiguration of the line reducing total pole numbers by approximately 65%
  • Replacement of approximately 15 kilometres of ageing infrastructure along the existing 19 kilometre transmission line
  • Undergrounding of a section of the line near the Karratha Airport Terminal
  • Project delivery included the following phases:
    • Design and Procurement Stage
    • Dismantling Old Line Stage
    • Clearing, Surveying and Setting-Out Stage
    • Bulk Earthworks Pad Construction Stage
    • Foundation Construction Stage
    • Pole Erection Stage
    • Transmission Underground Cable Installation Stage
    • Stringing and Cut-In Stage
    • Commissioning and Handover Stage

The project drew on Genus’ capabilities across design, construction and commissioning delivery.

The outcome

Commissioning of the 132kV Transmission Line was completed in November 2020, marking successful completion of the project.

The upgrade reinforced ageing infrastructure and strengthened security of supply across the North West Interconnected System (NWIS), supporting future energy demand across the Pilbara.

The works also improved local amenity through the removal of more than 200 poles from the corridor.